Interior Design for New Flat in Pune: A 60–90 Day Checklist from Possession Letter to Move-In
The possession letter is not the starting gun for shopping — it is the starting gun for a sequence. Here is the 60–90 day plan we walk new flat owners in Hinjewadi, Wakad, Baner, Tathawade and Punawale through.
The possession letter arrives, the keys follow, and suddenly everyone has an opinion about your kitchen. Before you open Pinterest, here is the honest truth about interior design for new flat in Pune: the homes that move in on time are not the ones with the fastest designer. They are the ones that did things in the right order.
This is the checklist we walk new flat owners through — a realistic 60–90 day plan from possession letter to move-in. It works whether your flat is in one of the new towers in Hinjewadi, Wakad, Baner, Tathawade or Punawale, or anywhere else in the city. We will also be upfront about where the plan stretches, because a checklist that pretends everything takes 45 days is not much use to anyone.
A quick note on that number. Our 45-day handover promise starts after final design approval and site readiness, and the date is written into the contract. *Terms & conditions apply. The weeks before that — snags, society paperwork, measurements and design — are part of your plan too, and that is what this guide is about.
The 60–90 day plan at a glance
| Phase | Typical window | What happens | Who drives it |
|---|---|---|---|
| Possession and snagging | Week 1–2 | Inspect, list defects, get builder to fix | You and the builder |
| Society rules and NOC | Week 1–3 (in parallel) | Interior work permission, timings, deposits | You and the society or facility manager |
| Measurement and brief | Week 2–3 | Site measurement, requirements, budget | You and the studio |
| Design and approval | Week 3–7 | Layouts, 3D, materials, final sign-off | Studio, with your decisions |
| Factory production | After approval | Cutting, edge banding, finishing, QC | Studio factory |
| Site work and installation | Overlaps production | Civil, electrical, ceiling, paint, then modular install | Studio site team |
| Deep clean and handover | Final week | Snag check, cleaning, walkthrough | Studio and you |
The design window depends on your collection: in our process, design takes 10–15 days for Essential, 20–30 days for Premium and 30–45 days for Lux. Delivery after design approval and site readiness is 45–60 days for Essential, 45–90 for Premium and 60–120 for Lux. That is why a simple modular-only job can comfortably fit inside 60–90 days from possession, while a Lux home with heavy customisation will run longer. Our process page lays out each step.
Before possession: what you can do now
If your possession letter has not arrived yet, you are in the best position of all. Most of the decisions that slow a project down can be made before you have the keys.
- Get the builder’s floor plan and electrical layout. These are rarely perfect, but they are good enough for preliminary layouts and a first budget.
- Visit a sample flat or a neighbour’s finished flat in the same tower. You will see real ceiling heights, beam positions and where the builder put the AC points.
- Decide your collection. Whether you need modular-only, or ceiling, electrical and painting as well, changes the whole schedule.
- Shortlist appliances. Hob, chimney, built-in oven, microwave, dishwasher, refrigerator size. Kitchen cut-outs depend on them.
- Book the first studio conversation. Design can begin on paper and be confirmed with site measurements later.
Doing this groundwork can take weeks off the post-possession timeline, because design starts with decisions already made.
Weeks 1–3: possession, paperwork and measurement
The first three weeks after you get the keys are about getting the flat ready to be designed for — not about choosing colours.
Week 1–2: possession and the snag list
Do this before a single piece of furniture is designed. Defects are far easier to get fixed before the builder’s team moves on, and far harder to fix once wardrobes are screwed to the walls.
Walk the flat with a notebook, a torch, a level app on your phone, and a bucket of water. Check:
- Walls and ceilings: cracks, uneven plaster, damp patches, especially on external walls and around windows.
- Flooring: hollow-sounding tiles (tap with a coin), chipped edges, uneven joints, slopes in bathrooms and balconies.
- Plumbing: run every tap and flush; check under sinks for leaks; pour water in bathrooms and balconies to see if it drains properly.
- Electrical: test every switch and socket; confirm the main board is labelled; check AC points and their positions.
- Doors and windows: alignment, locks, gaps, and whether sliding windows seal properly — important before the monsoon.
- Kitchen: platform level, sink outlet, gas pipeline point, chimney duct opening.
Photograph everything, list it, date it, and submit it to the builder in writing. Keep a copy.
The most important item on the list: seepage. Flats in newly completed towers often show damp on external walls in their first monsoon. Do not let anyone build a wardrobe onto a damp wall. Get it fixed and waterproofed first.
Week 1–3: society rules and NOC
Run this in parallel with snagging. Every society in Pune has its own rules for interior work, and getting them wrong can stop your site for days. Typical things to clarify with the society office or facility manager:
- Interior work permission or NOC: most societies need a written application before work starts.
- Working hours: many restrict noisy work to set hours and ban it on Sundays and holidays.
- Material movement: which lift can be used, at what times, and whether lift padding is required.
- Refundable deposit: some societies collect a deposit against damage to common areas.
- Debris disposal: where construction waste goes and who removes it.
- Worker entry: ID and registration requirements for site staff.
- Restrictions on changes: rules on altering external elevations, balcony enclosures, grills or the main door.
Share the rules with your studio before the schedule is set. A factory-made home helps here — most cutting and finishing happens off-site, so there is less noise and dust in the building — but installation still has to fit the society’s hours.
Week 2–3: measurement and brief
Once snags are fixed (or at least scheduled), get the site measured properly. Drawings from the builder’s brochure are not good enough for modular furniture; walls are rarely perfectly square, and a few millimetres matter.
Prepare your brief before the measurement visit:
- Who lives here, now and in five years? Parents moving in, a child arriving, work-from-home needs.
- How do you cook? Daily Indian cooking, baking, a separate wet kitchen in the utility.
- Storage reality check: how many wardrobes, how much hanging vs folded, where suitcases go.
- Must-haves vs nice-to-haves: a pooja unit, a study, a bar counter, a shoe cabinet.
- Budget: a range you are genuinely comfortable with. Be honest about it early — a designer can only protect a budget they know about.
Weeks 3–7: design and approval
This is where most delays actually start — not on site, but in decision-making. A design that changes every weekend cannot go to production.
What a good design phase includes:
- Layouts for every room, with furniture and appliance positions.
- Electrical and lighting plan — every light, switch and AC point — because ceiling and wiring depend on it.
- 3D views and a VR walkthrough, so you see the space before it is built. We show this before production through our 3D design and VR walkthrough.
- Material and finish selection — board, laminate or acrylic, handles, hardware.
- Final drawings and a fixed quotation, signed off by you.
Our advice, which occasionally costs us time: do not sign off a design you are not sure about just to start the clock. Changes after production starts are expensive and slow. Changes before sign-off are free.
After approval: factory, site and handover
Once the design is locked, the work splits into two tracks running side by side — the factory and the site — and then comes together for installation and handover.
Factory production
Once the design is signed and the site is ready, production starts. In our case that happens on our own 10,000 sq ft factory floor in Balewadi — boards cut, edges banded, shutters finished, and every unit checked before it leaves. Nothing on the joinery is subcontracted.
While production runs, site work happens in parallel. That parallel track is the main reason a factory-made home can be faster than one built entirely on site.
Site work and installation
The site sequence matters as much as the factory. For a Premium or Lux home, the typical order is:
- Civil modifications, if any.
- Electrical wiring and AC piping.
- False ceiling framing and boarding.
- Painting — first coats.
- Modular installation: kitchen, wardrobes, TV unit, vanities.
- Final paint touch-ups, lights, fixtures and hardware adjustment.
For an Essential (modular-only) home, the flat should already be painted and ready, and installation is the main site activity.
Deep clean and handover
Do not skip the deep clean. Interior work leaves fine dust in every drawer, channel and window track. Before handover:
- Professional deep cleaning, including inside every cabinet and wardrobe.
- A final walkthrough with the studio: every shutter, drawer, hinge and light tested.
- A handover snag list, if anything needs adjusting, with a date to fix it.
- Warranty documents and care instructions handed to you.
What real timelines look like in Pune’s growth corridors
Here are real homes we delivered in the areas where many new towers are getting possession, with recorded days to handover. Homes are anonymised.
| Home | Locality | Collection | Size | Final cost | Days to handover |
|---|---|---|---|---|---|
| 2 BHK, Kohinoor Sports Ville | Hinjewadi | Premium | ~700 sq ft | ₹7 L | 48 |
| 2 BHK, Orion Towers | Hinjewadi | Premium | ~700 sq ft | ₹8 L | 50 |
| 3 BHK, Life Republic | Hinjewadi | Premium | ~700 sq ft | ₹8 L | 50 |
| 2 BHK, Kohinoor Sapphire | Tathawade | Premium | ~700 sq ft | ₹7 L | 48 |
| 3 BHK, Kohinoor Sapphire | Tathawade | Premium | ~900 sq ft | ₹12 L | 62 |
| 3 BHK, Vision Venessa | Tathawade | Lux | ~1,300 sq ft | ₹15 L | 58 |
| 3 BHK, Parkways | Wakad | Lux | ~1,500 sq ft | ₹15 L | 80 |
| 2 BHK, Ganga Acropolis | Baner | Premium | ~900 sq ft | ₹8 L | 54 |
| 3 BHK, Jubilee Hills | Baner | Premium | ~1,200 sq ft | ₹12 L | 68 |
| 4 BHK, K Shire | Punawale | Essential | ~1,200 sq ft | ₹10 L | 70 |
| 4 BHK, K Shire | Punawale | Lux | ~1,500 sq ft | ₹16 L | 96 |
Two honest observations from that table:
- Several homes ran past 45 days. Larger homes and Lux homes with more customisation take longer. The 4 BHK Lux at K Shire took 96 days; the 3 BHK Lux at Parkways took 80. That is normal for that scope, and it is better to plan for it than be surprised.
- Compact homes in Hinjewadi and Tathawade landed close to the promise. The 2 BHKs at Kohinoor Sports Ville and Kohinoor Sapphire were handed over in 48 days.
If you are in one of these areas, our locality pages for Hinjewadi and Punawale show more of the work.
The mistakes that blow up the timeline
- Starting design before snags are fixed, then discovering the wall behind the wardrobe leaks.
- Not reading society rules, and losing days to a work stoppage.
- Deciding the AC after the ceiling is closed.
- Changing the design after production starts.
- Ordering appliances late, so the kitchen cut-outs cannot be finalised.
We have written a fuller list in why interior projects in Pune get delayed.
The whole checklist in one list
Screenshot this and tick it off as you go.
- Possession letter received; keys collected; meter readings noted.
- Snag walkthrough done with photos; written list submitted to the builder.
- Seepage, plumbing and electrical snags fixed and rechecked.
- Society interior-work rules read; NOC applied for; deposit paid if required.
- Working hours and lift-use rules shared with the studio.
- Appliances shortlisted, with model dimensions.
- Brief written: who lives here, cooking style, storage needs, must-haves, budget.
- Site measurement done by the studio.
- Layouts, electrical and lighting plan reviewed.
- 3D views and VR walkthrough reviewed; changes made now, not later.
- Materials and finishes selected; brands named on the quotation.
- Final design and fixed quotation signed; handover date in the contract.
- Production started; site work (civil, electrical, ceiling, paint) under way.
- Modular installation completed.
- Lights, fixtures and hardware adjusted and tested.
- Deep clean done, inside every cabinet.
- Final walkthrough; any handover snags listed with a fix date.
- Warranty documents and care instructions received.
Frequently asked questions
How long does interior design for a new flat in Pune take?
Plan for 60–90 days from possession for a straightforward home. Design takes 10–45 days depending on the collection, and delivery after design approval and site readiness ranges from 45–60 days (Essential) to 60–120 days (Lux). Larger and more customised homes take longer.
When should I start talking to an interior designer?
Before possession, if you can. You can finalise the brief, budget and even preliminary layouts from the builder’s drawings, then confirm with a proper site measurement once you have the keys.
Do I need a society NOC for interior work?
Most Pune societies require written permission before interior work starts, and many set working hours, lift-use rules and a refundable deposit. Check with your society office in the first week.
Should snags be fixed before interior work starts?
Yes. Seepage, plumbing leaks, hollow tiles and electrical faults are much easier to fix before furniture is installed. Never let a wardrobe go onto a damp wall.
Does the 45-day handover include design time?
No. The 45-day handover window starts after final design approval and site readiness, and the date is written into your contract. Larger or Lux homes have longer delivery windows.
Can I move in before everything is finished?
You can, but it usually slows the remaining work and makes cleaning harder. We recommend moving in after the deep clean and handover walkthrough.
If you have just got your possession letter, visit our studio and factory in Balewadi, Tuesday to Sunday — bring your floor plan and we will map out your 60–90 days together. Or start with the cost calculator.
While you're here
Want the number for your flat?
Ten seconds, no email gate, no “an advisor will call you with a price.”
Price your home